234241
222576
Business  

Coastal GasLink project continues pipe installation

GasLink reports progress

Pipe installation and clearing continues in the first two spreads of the Coastal GasLink pipeline through the Peace Region.

In an October update, the company reported 21% of pipe installed in the project's first spread, which runs 92 kilometres from Groundbirch to the Brule Mines area. No pipe has been installed in the second spread, which runs 48 kilometres to the McLeod Lake area. The area is 59% cleared, according to Coastal GasLink.

“We’re reaching peak construction on the Coastal GasLink right-of-way while also continuing to progress construction on our compressor and meter station facilities,” the company said.

The company reported 3,488 workers as of Sept. 30. There were 82 workers reported at Sanataa Lodge and 206 workers at Sukunka Lodge.

The company says site preparations along with earthworks and piling for the Wilde Lake compressor station continues in Groundbirch. Civil works have begun for a third worker lodge at Mt. Merrick.

Elsewhere, the company says 26% of pipe has been installed between Bear Lake and Vanderhoof. Another 4.5% of pipe has been installed between Burns Lake and Houston, and 1% in the final spread between Morice Lake and Kitimat.

The $6.6-billion pipeline is a key piece of infrastructure for LNG Canada. Two Fort St. John contractors, Surerus Pipeline and Macro Industries, have joint venture projects hired to build segments of the pipeline.

Surerus Murphy is building the first two sections of the pipeline between Groundbirch and McLeod Lake. It put the project's first pipe segments in the ground in July.

Macro Spiecapag is building 85 kilometres of pipeline between Burns Lake and Houston, as well as the final 84 kilometres from the Morice Lake area to Kitimat.



More Business News

229439
232645
Data from CryptoCompare
RECENT STORIES
229862
228921
218881
Castanet Proud Member of RTNDA Canada
232508
Press Room
225430